Level of Effort Items

B
Brian Yung 👤 Member for 17 years 3 months
D
Dieter Wambach 👤 Member for 19 years 5 months

Dear Brian

You’ll assign ALL predecessors with a SS relationship and ALL successors with a FF relationship. The first predecessor automatically start the LoE, the last successor finish it.



Regards

Dieter

B
Brian Yung 👤 Member for 17 years 3 months

Dear Dieter,



What happens when you have a group of activities that you aren’t sure about which one would start first but the start of anyone of them will be the start of your LOE. The same goes for the end.



What I’ve done up to now was:

add the activities in the group twice as the predecessor. One with an SS relationship and the other with a FS relationship.



I’m not too convinced that this is a good way of doing it.



would you have any other suggestions?



Regards

D
Dieter Wambach 👤 Member for 19 years 5 months

Dear Brian



Just do it as you did in P3: SS from predecessor to LoE then FF from the LoE to the activities determining its end as a successor. LoE has no own duration (same as Hammock).LoE, same as Hammock, isn’t able to drive successors.



Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts