Dear Brian
Youll assign ALL predecessors with a SS relationship and ALL successors with a FF relationship. The first predecessor automatically start the LoE, the last successor finish it.
Regards
Dieter
Dear Dieter,
What happens when you have a group of activities that you arent sure about which one would start first but the start of anyone of them will be the start of your LOE. The same goes for the end.
What Ive done up to now was:
add the activities in the group twice as the predecessor. One with an SS relationship and the other with a FS relationship.
Im not too convinced that this is a good way of doing it.
would you have any other suggestions?
Regards
Dear Brian
Just do it as you did in P3: SS from predecessor to LoE then FF from the LoE to the activities determining its end as a successor. LoE has no own duration (same as Hammock).LoE, same as Hammock, isnt able to drive successors.
Regards
Dieter