I know of a few people who are encounter problems similar to yours and gone back to using MS Project 2003. One of the reasons I’m wary of upgrading at the moment.
No consolation to you I know, but you’re not alone in your frustration.
I have only started working with the programme but what is very apparent is that the programme was developed by a mix and match of users in both MSP03 and MSP07.
Have tried all of the above with no luck.
Seriously have spent around 3wks with this programme exporting, importing, copying, pasting, calendars etc.
The latest Service Pack is 1 for 2007.
I also have done detect and repair and today unistalled and reinstallled 2007.
So after all that I think im going to try the programme with a different software it jsut isnt manageable for this programme.
As far as I’m aware, performance will be more affected by file size or PC / Laptop performance than the amount of task activities, so it would depend on how many macros you have, logos in the headers, etc. etc.
What I do know for certain is that 2,500 tasks is nowhere near its limitations.
Also, was the plan built in MS Project 2007 or migrated over from 2003 / 2000 / 98? There may have been a bit of file corruption if it was migrated.
Have you got the latest service pack?
Have you tried copying and pasting into a blank schedule? (Making sure it has the same holidays etc. as the old one)
In 2003 there was a function called Detect and Repair, I’m not sure if it is available in MS Project 2007 but you might want to try that if it is (Back up your file onto a disk or something first). It automatically finds and fixes errors, not only with MS Project, but all shared Office components.
The very last resort... you can always reinstall MS Project 2007 if you have the administrative rights for your PC / Laptop.
Regards,
Darren
EDIT: You can see if the problems you are experiencing are listed as bugs with Microsoft, if not report it and give them both barrels!! :)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Maby this link kan help you
http://go.microsoft.com/fwlink/?LinkID=92795
see page 97
Karen,
MS Project 2007 (Std or Pro the same) is definitely not a stable product; you should move back to MS Project 2003
Alexandre
Karen,
I know of a few people who are encounter problems similar to yours and gone back to using MS Project 2003. One of the reasons I’m wary of upgrading at the moment.
No consolation to you I know, but you’re not alone in your frustration.
Regards,
Darren
Darren
I have only started working with the programme but what is very apparent is that the programme was developed by a mix and match of users in both MSP03 and MSP07.
Have tried all of the above with no luck.
Seriously have spent around 3wks with this programme exporting, importing, copying, pasting, calendars etc.
The latest Service Pack is 1 for 2007.
I also have done detect and repair and today unistalled and reinstallled 2007.
So after all that I think im going to try the programme with a different software it jsut isnt manageable for this programme.
Hi Karen,
As far as I’m aware, performance will be more affected by file size or PC / Laptop performance than the amount of task activities, so it would depend on how many macros you have, logos in the headers, etc. etc.
What I do know for certain is that 2,500 tasks is nowhere near its limitations.
Also, was the plan built in MS Project 2007 or migrated over from 2003 / 2000 / 98? There may have been a bit of file corruption if it was migrated.
Have you got the latest service pack?
Have you tried copying and pasting into a blank schedule? (Making sure it has the same holidays etc. as the old one)
In 2003 there was a function called Detect and Repair, I’m not sure if it is available in MS Project 2007 but you might want to try that if it is (Back up your file onto a disk or something first). It automatically finds and fixes errors, not only with MS Project, but all shared Office components.
The very last resort... you can always reinstall MS Project 2007 if you have the administrative rights for your PC / Laptop.
Regards,
Darren
EDIT: You can see if the problems you are experiencing are listed as bugs with Microsoft, if not report it and give them both barrels!! :)