dig foundations
pour foundations
set steel in basement
set steel in lobby
set steel 2nd floor and repeate for as many floor that you have
set roof steel
set exterior skin and windows and repeate for as many floor that you have
fit out basement
fit out lobby
fit out 2nd floor and repeate for as many floor that you have
done
none
Ronald, 3 storey construction is not the same as highrise building construction.
Why? Among the many reasons, one of them, is logistic requirements...
hiiiii
Could you pls send me the schedule for the high rise building at
[email protected]
Note : I am attending PMI -SP classes these days and learnt about this most usefull site during classes.
Hi Arman,
I found your post #22 extremely interesting, pointing out as it did the implausibility and impracticality of Charlies skyscraper. Im sure it wont be too long before Charlie responds with a detailed explanation of how to resolve all of the difficulties.
Im sure hell also get round to supplying the schedule that he promised to so many people as well, however, I wont be holding my breath.
Chris Oggham
Hi Charles,
Would you pls send me a copy too?
Email: [email protected]
Thnks
Abhay
Sensei,
I really appreciate your idea and I would like to share any idea...
To start with...
1. If our building is 1,500 storeys excluding basements and podium and assuming a fast 5 day per floor structural works cycle using 5 complete form sets, etc...that would take us 7,500 calendar days;
2. At 4,500 m high (14,760 feet) would be beyond air traffic height limitation. We may require sovereignty of our air space;
3. I suggest we need a high altitude helicopter to do that;
4. etc...
Arman
Hi Charles,
Would you pls send me a copy too?
Email: [email protected]
Thnks
luigi
Hi Charles,
Would you pls send me a copy too?
Email: [email protected]
Thnks
luigi
Its really exciting..
Whats the Built up area you are planning for..
& What is the FSI, Plinth area etc you are planning for..so that some conceptualisation can start off...
Regards
J Sridhar
Ronald,
The one Im thinking of generating start design phase (concept, schematic, design development, contract documentation) Tender Phase, Construction Phase and Post Construction (defect liability period).
The Skycraper I have in mind is the tallest in the Universe 1500 storey high above ground level (4,500 meters), compose of three towers (skycraper) within built up area (podium and retails).
fellow PPers,
I believe that even though i did most of my planning was up to three floors , planning for a skycraper from first floor up will almost be the same save for some variation in the design and use of the floor it will be typically a copy of the floor preceeding it .
Am I right? So Charles send me a sample at [email protected] to learn some words, verbs and terminology planners are using when planning a skycrapper from ground up.
Regards,
Hi Sensei Charles,
Are you involve in the construction of the highest building now? Can u please share to us your construction programme?
Regards,
kier
HI,
Would you please send me the SKYCRAPER programme and activities on my e-mail: [email protected]
thanks.
Dear All,
Im surprise with the response. Very few are involve in building works, most are involve with other trade. What does this "sample Skycraper CPM means, maybe someday there will be migration to building works.
In my reply no 2
How high is your SKYCRAPER???? nobody answer
You want the sample of the Highest Building in Planet Earth. no answer
Also provide a typical floor area. no answer
"Maybe we can come up with something." This is very important.
What really I have in mind is a collaoboration of the best of the best plannning planet can offer. We, not me alone, will prepare a CPM Schedule using hypothetical tallest tower/skycrapper in the Universe.
How to do this?????
It will be unfold if our work will give us free time.
Cheers,
Sensei
Hi Charles ,
Havent receiced your skycraper program.
Cheers
kier
Hi Charles,
Would you pls send me a copy too?
Email: [email protected]
Your help would be appreciated.
Cheers,
Cherry
Hi Charls
Could you pls send me a copy too at my mail adress [email protected]
Regards
Sridhar
Hi Charles,
Would you pls send me a copy too?
Email: [email protected]
Thnks
Gencay
Hi Charles,
Would you pls send me a copy as well?
Email: [email protected]
Thnx
Mohd
Hi Charles,
could you please drop me copy as well , [email protected]
thanks
sam
Hi Charls, drop a copy to me as well at [email protected]
your help will be appreciated.
regards,
Charlies still hawking round that WBS they used on the tower of Babel ;o)
Hi Charles,
By any chance, do you have any logistics plan for the high-rise buildings. I have asked it before on PP, but no help. What I am using now is totally unpresentable. If you have any, plz share. Can send the mail on [email protected]
Hi Charles,
While you are handing out the wbs for the highest building on Planet earth some guy in the middle east is making one double the height...so lets see how upto date the WBS really is..do send me one at [email protected]
Best regards..
Hi Charles,
Could you please send me any sample projects in High rise building.My mail [email protected]
Regards,
kier
Hi,
How high is your SKYCRAPER????
You want the sample of the Highest Building in Planet Earth.
Also provide a typical floor area.
Maybe we can come up with something.
Cheers,