The reason I use this information is for my progress reporting, If I am going to a site to mark up progress I can have my status day set and bring a print off of the programme while marking up the progress.
As I only have a couple of years planning experience, I find that it is a good starting point for my progress reports and have become dependant upon it.
Also when I have to circulate my progress reports all high level management like to see it, well from my experience anyway.
It helps a lot to show the Status Date as a vertical solid red line on the Gantt Chart with Format, Gridlines.
Using your example, which is about the current schedule rather than the Baseline although the approach is the same in both cases, lets suppose that the first day was Monday and the 5 days duration runs from Monday to Friday.
The Status Date, the day up to which you are reporting progress, is the end of Tuesday.
The difference between the Status Date and the start date of the Task is 2 days.
So for "Planned Percentage" you need a formula in a spare duration field to calculate this difference and then divide it by the task duration, ie:
((status date - start date)/duration)*100 = (2/5)*100=40.
Then a formula in a spare text field to add a space and the "%" sign, ie:
[planned percent]&" %".
But the important piece of factual information that is missing from your example is which of the 2 days was worked, Monday or Tuesday. You have the Actual Duration but not the Actual Start.
If Monday, then the task started as planned, was worked on for one day and then interrupted. So nothing was done on Tuesday and that 1 day of unused duration has to be re-scheduled into the future. The 3rd button on the Tracking Toolbar will do this. The remaining duration is now 4 days and the finish date is now not Friday but the following Monday. At this point you should do the last step and decide whether to re-estimate the Remaining Duration, or leave it at 4 days.
If Tuesday, then the Actual Start was Tuesday and the Task was worked on continuously up to the Status Date.
First you put the Actual Start Date into the Actual Start field in the Tracking Table, which shoves the task 1 day to the right, then use the 2nd button on the Tracking Toolbar to "Update as scheduled" which will show the Actual Duration occurring on the correct day.
What you must not do is leave 1 day of unused duration on the left of the Status Date, because it can only be done in the future.
If you dont re-schedule Tuesday (if the start was Monday) or set the actual start to Tuesday (if the start was Tuesday) then you dont get to see the effect of losing 1 day, ie that the finish date is now the Monday following Friday.
Doing the calculation to see that "Planned Percent" = 40% is easy to do and nice to know, but what part does it play in anything? Sure, you can say "Planned Percent" = 40% and % Complete = 20%, but how do you use this information?
Darren thanks for your help Im goin to check out that link now.
When talking about Planned % Complete, yes the amount of duration I have gone through when I dropline my progress date to the schedule.
I’m using MSP 2007 but finding many bugs…
Trevor thanks also for your very helpful reply.
Basically what I use the Planned % Complete for is a way of measuring where I planned to be on the job and once I do the dropline and put in actual % Complete on a project then I can see straight away whether I am ahead or behind!!!
For example:
Activity: Pour Foundations 5 day duration (100%)
Actual Percentage: I have only 1 day worked (20%)
Planned Percentage: I Should have 2 days work done from my schedule (40%)
Obviously this is showing it in a simplified version I have a master programme with approx 3000 activities which I am still setting up and at the end of the month need to start reporting on this.
So do I use the macro or the way you have explained it to me?? NEw user to MSP 07 so the easiest way is probably the best!
A % of anything requires a numerator and a denominator.
It would be easier to understand exactly what you mean by "% Planned Complete" if you can tell us what numerator and denominator you have in mind.
However, meanwhile, I can guess.
Two possilities can be considered, the task baseline and the task as it is in the current plan, which might very likely be different from the baseline in all respects.
Baseline first. The question is, roughly, if the task had started on the baseline start date, and been worked on continuously up to the status date, what fraction of the total baseline duration would be used? The denominator is the total baseline duration, or TBD. The numerator is what we can call the "planned baseline duration up to status date", or PBDUTSD.
To find this, you just need to subtract the baseline start date from the status date.
Before you do this, you need to test for whether the baseline start date is to the right of the status date (task wasnt planned to start yet so % Planned Complete = 0) or if the status date is to the right of the baseline finish date (task was planned to be finished already so % Planned Complete = 100).
This is fairly easily done using one of the datediff functions and the IIF function in a couple of formulae in a couple of spare duration and text fields.
Similarly for the current task but with the current start date and current finish date.
So they are easy enough to calculate but what use are they?
Sorry to hear of your troubles with MS Project, I had a similar experience when I went from MS Project to SAP PS.
When you become more familiar with a tool you then understand its limitations and learn to work with what you’ve got now, not what you had before.
In the end most tools have their plus points and their minus points and there is not that much to choose between them.
As to your query, I’ve got a couple of questions for you to see if I can understand the problem a little better.
When you talk about Planned % Complete I’m making the assumption that you mean how far through the task you have progressed (Duration) and not the percentage of effort you have burned (Actuals), is this correct?
Simply put a task that has a 10 day duration with 80h work can have different % Completes in MS Project. This means you can have a task that is 50% Complete, meaning it has 5 days remaining and at the same time 25% Work Complete, meaning you have 60h work remaining.
The second question is what MS Project version are you using? 2003 or 2007?
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
The reason I use this information is for my progress reporting, If I am going to a site to mark up progress I can have my status day set and bring a print off of the programme while marking up the progress.
As I only have a couple of years planning experience, I find that it is a good starting point for my progress reports and have become dependant upon it.
Also when I have to circulate my progress reports all high level management like to see it, well from my experience anyway.
Your help on this is much appreciated!
No doubt Ill be back on soon for more!
Karen,
It helps a lot to show the Status Date as a vertical solid red line on the Gantt Chart with Format, Gridlines.
Using your example, which is about the current schedule rather than the Baseline although the approach is the same in both cases, lets suppose that the first day was Monday and the 5 days duration runs from Monday to Friday.
The Status Date, the day up to which you are reporting progress, is the end of Tuesday.
The difference between the Status Date and the start date of the Task is 2 days.
So for "Planned Percentage" you need a formula in a spare duration field to calculate this difference and then divide it by the task duration, ie:
((status date - start date)/duration)*100 = (2/5)*100=40.
Then a formula in a spare text field to add a space and the "%" sign, ie:
[planned percent]&" %".
But the important piece of factual information that is missing from your example is which of the 2 days was worked, Monday or Tuesday. You have the Actual Duration but not the Actual Start.
If Monday, then the task started as planned, was worked on for one day and then interrupted. So nothing was done on Tuesday and that 1 day of unused duration has to be re-scheduled into the future. The 3rd button on the Tracking Toolbar will do this. The remaining duration is now 4 days and the finish date is now not Friday but the following Monday. At this point you should do the last step and decide whether to re-estimate the Remaining Duration, or leave it at 4 days.
If Tuesday, then the Actual Start was Tuesday and the Task was worked on continuously up to the Status Date.
First you put the Actual Start Date into the Actual Start field in the Tracking Table, which shoves the task 1 day to the right, then use the 2nd button on the Tracking Toolbar to "Update as scheduled" which will show the Actual Duration occurring on the correct day.
What you must not do is leave 1 day of unused duration on the left of the Status Date, because it can only be done in the future.
If you dont re-schedule Tuesday (if the start was Monday) or set the actual start to Tuesday (if the start was Tuesday) then you dont get to see the effect of losing 1 day, ie that the finish date is now the Monday following Friday.
Doing the calculation to see that "Planned Percent" = 40% is easy to do and nice to know, but what part does it play in anything? Sure, you can say "Planned Percent" = 40% and % Complete = 20%, but how do you use this information?
Darren thanks for your help Im goin to check out that link now.
When talking about Planned % Complete, yes the amount of duration I have gone through when I dropline my progress date to the schedule.
I’m using MSP 2007 but finding many bugs…
Trevor thanks also for your very helpful reply.
Basically what I use the Planned % Complete for is a way of measuring where I planned to be on the job and once I do the dropline and put in actual % Complete on a project then I can see straight away whether I am ahead or behind!!!
For example:
Activity: Pour Foundations 5 day duration (100%)
Actual Percentage: I have only 1 day worked (20%)
Planned Percentage: I Should have 2 days work done from my schedule (40%)
Obviously this is showing it in a simplified version I have a master programme with approx 3000 activities which I am still setting up and at the end of the month need to start reporting on this.
So do I use the macro or the way you have explained it to me?? NEw user to MSP 07 so the easiest way is probably the best!
Kare,
A % of anything requires a numerator and a denominator.
It would be easier to understand exactly what you mean by "% Planned Complete" if you can tell us what numerator and denominator you have in mind.
However, meanwhile, I can guess.
Two possilities can be considered, the task baseline and the task as it is in the current plan, which might very likely be different from the baseline in all respects.
Baseline first. The question is, roughly, if the task had started on the baseline start date, and been worked on continuously up to the status date, what fraction of the total baseline duration would be used? The denominator is the total baseline duration, or TBD. The numerator is what we can call the "planned baseline duration up to status date", or PBDUTSD.
To find this, you just need to subtract the baseline start date from the status date.
Then:
% Planned Complete = (status date - baseline start date)/baseline duration)
Before you do this, you need to test for whether the baseline start date is to the right of the status date (task wasnt planned to start yet so % Planned Complete = 0) or if the status date is to the right of the baseline finish date (task was planned to be finished already so % Planned Complete = 100).
This is fairly easily done using one of the datediff functions and the IIF function in a couple of formulae in a couple of spare duration and text fields.
Similarly for the current task but with the current start date and current finish date.
So they are easy enough to calculate but what use are they?
Karen
Yes you can, but I use a macro to work it out - too bulky for this answer - send me your e-mail & I will forward what I use.
Karen,
Try looking at this discussion.
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=4&Top=38398
Reply #2 from Niek Zonneveld might be what you’re after.
Regards,
Darren
Hi Karen,
Sorry to hear of your troubles with MS Project, I had a similar experience when I went from MS Project to SAP PS.
When you become more familiar with a tool you then understand its limitations and learn to work with what you’ve got now, not what you had before.
In the end most tools have their plus points and their minus points and there is not that much to choose between them.
As to your query, I’ve got a couple of questions for you to see if I can understand the problem a little better.
When you talk about Planned % Complete I’m making the assumption that you mean how far through the task you have progressed (Duration) and not the percentage of effort you have burned (Actuals), is this correct?
Simply put a task that has a 10 day duration with 80h work can have different % Completes in MS Project. This means you can have a task that is 50% Complete, meaning it has 5 days remaining and at the same time 25% Work Complete, meaning you have 60h work remaining.
The second question is what MS Project version are you using? 2003 or 2007?
Regards,
Darren