hi manik,
can u please share the manual with me.
i am a project scheduler, and i need to customize my report using p6 urgently.
please help as it will be greatly appreciated.
thanks and regards,
PRATISHTHA
PLANNING AND INTERIORS
It was a pleasure
Dieter
Hi Dieter,
So many thanks mate. I have receive dthe file. I am so very thankful to you for helping me.
Many Thanks.
Regards,
Manik
Hi Manik
Just a little patience. Until now I didnt receive an error message. I sent it to both adresses.
Dieter
Hi Dieter,
I havent received it yet :-(
regards,
Manik
Its done
Dieter
Hi Dieter,
Thanks a lot for your help.
You can send the files to [email protected] and copy them to [email protected]
About your comment we have already asked them to do so and the IT guys will come up with something which will help us. But it may take sometime as they are already working on something with the P6 database.
Regards,
Manik
Hi Mainik
One remark: Your IT people should put some of the documentation files onto the server.
Dieter
Hi Manik
If Youll send me your Mail address, Ill send it. Even zipped, the mail will have >7MB. Check first if you can receive that size.
Regards
Dieter
Hi Dieter,
I dont have the CD as i am using P6 in my company and the software is loaded at our server in USA and all the project controllers across the globe use it via CITRIX imaging server. So no one will be having the CD of documentation of P6 and that is the problem. Can you provide me with the document you are talking about or the part which will help me. Or any website where i can get that.
Regards,
Manik
Hi Manik
The third cd out of the set delivered by Primavera is the documentation cd. There you can find this and other helpful files.
Regards
Dieter
Hi Dieter,
So many thanks for your help but where do i find this PMREFMAN.pdf
Warm Regards and Best Wishes,
Hi Manik
If youll have a look into the "PMRefMan.pdf" --> Customizing Projects --> Customizing Reports --> Using the Report Editor.
This probably will be the best introduction. the best way will be then to learn it by yourself.
Some hints:
Allways work with a copy.
If youll need an additional data item to the wizzard, add another item with the wizzards, to replace it with the editor.
Time distributed data: Allways create the table with the wizzard, no chance to do it with the editor.
Use the preview button.
There is an exit "Cancel".
Good luck!
Dieter