i think it’s unclear if Ijaz wants the resource curve to show up for each assignment or if they want the resource usage profile. it seems to me he wants the histogram of resource usage.
try clicking on the resource usage profile button, then be sure to adjust the display options so that it will show the current project resources. then pick one and it will show the "s-curve" as a bar chart on the right.
Thanks Salahuddin, your solution worked well for activities but I still have problem of getting S-curves resource-wise like for boilermaker, fitter etc. If you can sort it out please write.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
i think it’s unclear if Ijaz wants the resource curve to show up for each assignment or if they want the resource usage profile. it seems to me he wants the histogram of resource usage.
try clicking on the resource usage profile button, then be sure to adjust the display options so that it will show the current project resources. then pick one and it will show the "s-curve" as a bar chart on the right.
Salah,
Thanks for the reply. But what you have mentioned is missing in Version P5. If you also have version P5 then you can look what I am talking about.
Thanks
Ijaz
Ijaz,
For particular resource "S" curve, please follow the steps,
> Choose project
> Resource assignments
> Select the resource assignment to which you want to assign a resource curve.
> To display curve column, click the display options bar
> Choose columnns customize
> Select curve from the general group and add it to the selected list
I hope this will help you and research for printing options.
Salah
Thanks Salahuddin, your solution worked well for activities but I still have problem of getting S-curves resource-wise like for boilermaker, fitter etc. If you can sort it out please write.
Thanks for your help
Ijaz
Ijaz,
Well i am using P6 and P3 it should be same as p6.
However please check.
Follow the steps for "S" curve.
> View
> Show on Bottom
> Activity Usage Profile
> Right click within the profile and select Cost or Unit
> click on Graph tab and check on calculate average
> ........
I hope this will help you, if not let me know through personel email, i will walk you through.
Regards
Salah
I am using version P5
Ijaz,
Which version of Primavera P3/P6.
Salah
Do a search on s curves in pp, there should be enough info on the threads to help.