Manhrs Loading In P6

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Praju

This will depend on the duration type.

I assume, that your type is "Fixed duration and units". the a change of budgeted units won’t impact the duration, just units/time.

Regards

Dieter