WBS level duration in PM5/6

D
David Kelly 👤 Member for 21 years 8 months

The duration shown in a WBS activity is based on the WBS activity’s calendar. When you press F9, the WBS duration is back-calculated based on it’s start and finish dates on the calendar you have chosen.



***** NOTE ******



The duration of a level-of-effort activity is based on the Early dates of the hammocked activities, a WBS summary is based on Planned dates BE CAREFULL!!