Did you agree to the milestones prior to the submission of the Clause 14.1? If not, have they been introduced since the submission but prior to the consent for use?
Also, did the Engineer Instruct you to Accelerate the works? (Please note the two key words Instruct and Accelerate)
Im a litte amused that the Client has advised you to submit a claim, sounds a bit like a set-up to me.
Can you give me a wee bit more info?
Cheers,
Davie.