Date scheduling issue

A
Akhilesh Shukla, CCE EVP PMP 👤 Member for 20 years 10 months

Dear Manfred,



Please ensure that you have saved your baseline schedule in peoper way i.e. assigning it (the schedule U want to keep as basline) as primiry baseline.



The symptoms as U mentioned are frequent when baseline is not saved.



Regards



Akhilesh

C
Cyril Armentia 👤 Member for 23 years 3 months

Hi,



You are confused between ’Primary Baseline’ and ’Original’ baseline.



Possibly that you haven’t created your ’Original’ baseline yet or maybe you have not assigned your ’Original’ baseline into the primary baseline window.



If the primary baseline is ’current project’ dates for your baseline will also change when you change your schedule.



Check your primary baseline window. It must have the assignment of your ’original’ baseline.



Cheers,

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts