Imprting baseline

K
K D 👤 Member for 18 years 8 months

Hi Selcuk.

I’m sure what I talking . :-)

After you reconfigure the option I presented, you create a new baseline in Maintain baseline function, and then assign the new baseline to Project BL and Primary BL.



Regards

S
Selcuk Erguden 👤 Member for 19 years 1 month

Hi,



About Question 2: There are two steps to import a baseline. First step, maintain BL and second one is Assign BL as Project BL and also Primary user BL.

Are you sure that you realized these two steps?



Regards,

SE

K
K D 👤 Member for 18 years 8 months

Hi.

question 1 : There is BL Project start value in Date group. Usually it is identical to BL Project early start.

K
K D 👤 Member for 18 years 8 months

Hi.

question 2 : maybe you can try on changing this option. Goto Admin -> Preference -> Earned value -> in Earned value calculation , change value to "Budgeted value with current date"



Now create the baseline again and see whether the baseline date change.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts