Fixed task duration

F
Forum Guest 👤 Member for 17 years 5 months
M
MK TSE 👤 Member for 24 years 4 months

Thanks. All in bar style, just finish a test on Project2k and work. I do a backward scheduling and store the late start/finish in a custome field. Then do the forwars scheduling scheduling again to back to early dates. Now display both early and late bars by Bar style.

F
Forum Guest 👤 Member for 17 years 5 months

I think what MKTSE means, is make sure your task has a 3 day float and only 1 day duration. In the Bar Style Options, put Float bar over the other bars defined in the Bar Style Options i.e. put the float bar as the last row in your bar definition.



SE

F
Forum Guest 👤 Member for 17 years 5 months

China - thanks very much for your reply but I am not sure how do do what you suggest. Can you describe what I do from Gantt Chart view as I have tried all the buttons on the task information box with no success.



Thanks again



Chris

M
MK TSE 👤 Member for 24 years 4 months

Use the calcaulated float the work out the start/finish dates of float bar and put the bar against the normal earier bar.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts