p5 to p3 conversion date problem
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
P5 is using the HOUR as basis of calculation, when P3 is using the DAY !
AS Benjamin said there is not a solution for that. Primavera promized to solve the issue later on as an enhansment request to P6 from the Construction industry !!!
We are still waiting..
Regards
After a lot of discussion with the vendor, the conversion is not always going to be perfect. Allegedly, there things that you can do to the P5 schedule to make the backward conversion better, but I have never seen it done. I think your calendar(s) is this issue.