Cost Loading

S
sunil kumar 👤 Member for 20 years 8 months
S
sunil kumar 👤 Member for 20 years 8 months

Hi Imran

ok once i establish my resource database & allocate it to activities... cost parameters will be loaded for example Budgeted cost...



thanks for the reply.

I
Imran Arshad 👤 Member for 18 years 7 months

Dear Sunnil,

In P6 when you define resources u also incooporate their cost and same for expense and after assigning these resource you get cost loaded on your schedule.





Imran