Labour calculation

M
Mike Testro 👤 Member for 20 years 6 months

Hi Shaik

It is a good idea to check the original date of a thread before taking time to prepare a detailed answer.

It may not be appreciated 4 years later.

Best regards

Mike Testro

S
shaik yakub 👤 Member for 18 years 10 months

Nornally it is 60Mhrs - 85 Mhrs with an AVG of - 75 Mhrs/Ton However depends upon the type of work (Raft,Wall,Column,Slab)& dia of rebar.

 

Regards,

Shaik

R
Rubas M. Kutty 👤 Member for 18 years 7 months

Assumed a 5-day week for the inputs

The production rates:



75 mm screed : 3 sqm/hr

Render : 3 sqm/hr

Carpet tile : 3 sqm/hr

Vinyl sheet : 5 sqm/hr.



PS: There was a miscalculation w.r.t Vinyl sheetings.



Regards,


N
Nar Thap 👤 Member for 18 years 9 months

Can somebody of you who answered pls. also post the basis for coming to that result ? Helpful for members. rgds,

K
Kieran Thomson 👤 Member for 22 years 4 months

For the screed get it mechanicaly pumped and laid, should take a week and remember it needs to go off before you work on it whatever way its thrown in, and dry before you lay anything on it (that could take up to 7 weeks).

J
James Thorpe 👤 Member for 20 years 9 months

Thanks kutty for you help.



Other members comments would also be appreciated.

R
Rubas M. Kutty 👤 Member for 18 years 7 months

Hi James,



These are the rough figures.



A) 4.5 nos

B) 6 nos

C) Carpet tiles - 3.5 nos

Vinyl sheets - 6.3 nos

I am not having data for the matting. Trust this helps.



Regards,

Forum Sponsor

Top Posters

JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts