Yes, you can assign dates to Steps, but they will not ‘roll-up’ to your activity dates. Just add two User-Defined-Fields (UDF) to your Steps tab and make then data type: Date. Title the fields with “Start” and “Finish” or whatever you like. Good luck!
Member for
16 years 2 monthsRE: Weight percentages
Thanks Ronald..
Member for
22 years 10 monthsRE: Weight percentages
Yes, you can assign dates to Steps, but they will not ‘roll-up’ to your activity dates. Just add two User-Defined-Fields (UDF) to your Steps tab and make then data type: Date. Title the fields with “Start” and “Finish” or whatever you like. Good luck!
Member for
16 years 2 monthsRE: Weight percentages
in P6 i mean...
Member for
16 years 2 monthsRE: Weight percentages
Can we assign dates to the steps? it could be the planned or target dates to achieve the identified steps
Member for
19 years 9 monthsRE: Weight percentages
Please ignore last two replies.
hope this one apears all right on the web page.
Percntage.
Is the amount of work done in terms of physical % complete or duration % complete or units % complete.
Whichever you are using in Primavera P5. value for this ranges between 0-100.
Weight Percentage and Weight.
Lets sey you have an activity which will be complete when A, B and C will be completed ( consider A, B and C as steps to that activity)
Now
You have to assign weight to each of this step,, how imp it is or what proportion of work it will cover for an activity
Just for an example.
Activity A
weight % = 40
weight = 2.0
Activity B
weight % = 40
weight = 2.0
Activity C
weight % = 20
weight = 1.0
When you change weight , percent weight should change automatically..
Lets suppose there are only 2 steps, so
Activity A
weight % = 50
weight= 2.0
Activity B
weight% = 50
Weight = 2.0
Hope this helps.
If I am incorrect please correct me.
Thanks
Keep asking and answering
Member for
19 years 9 monthsRE: Weight percentages
Percntage.
Is the amount of work done in terms of physical % complete or duration % complete or units % complete.
Whichever you are using in Primavera P5. value for this ranges between 0-100.
Weight Percentage and Weight.
Lets sey you have an activity which will be complete when A, B and C will be completed ( consider A, B and C as steps to that activity)
Now
You have to assign weight to each of this step,, how imp it is or what proportion of work it will cover for an activity
Just for an example.
Activity steps weight (%) weight
Activity A 40 2.0
Activity B 40 2.0
Activity C 20 1.0
When you change weight , percent weight should change automatically..
Lets suppose there are only 2 steps, so
Activity steps weight (%) weight
Activity A 50 2.0
Activity B 50 2.0
Hope this helps.
If I am incorrect please correct me.
Thanks
Keep asking and answering
Member for
19 years 9 monthsRE: Weight percentages
Percntage.
Is the amount of work done in terms of physical % complete or duration % complete or units % complete.
Whichever you are using in Primavera P5. value for this ranges between 0-100.
Weight Percentage and Weight.
Lets sey you have an activity which will be complete when A, B and C will be completed ( consider A, B and C as steps to that activity)
Now
You have to assign weight to each of this step,, how imp it is or what proportion of work it will cover for an activity
Just for an example.
Activity steps percent weight (%) weight
Activity A 40 2.0
Activity B 40 2.0
Activity C 20 1.0
When you change weight , percent weight should change automatically..
Lets suppose there are only 2 steps, so
Activity steps percent weight (%) weight
Activity A 50 2.0
Activity B 50 2.0
Hope this helps.
If I am incorrect please correct me.
Thanks
Keep asking and answering