Hi pals,



The manual is still under preparatory stage.



What we were asking from last so many days is some guidelines from Mr. Abhijit Kale, which he never turned up.



So, u may send PM to Abhijit kale for help rather than reading these posts?



Cheers,



Rav

T
Tommy Nug 👤 Member for 18 years 7 months

Hey guys,



Why we dont have any links to down load this manual instead of showing your email. It wastes a lot of time!!!

G
Galing Galing 👤 Member for 18 years 8 months

gentlemen,

please, whoever has a copy of "Planning & Project Control Manual" readily available, kindly send me a copy asap to

[email protected]. Thanks a lot.

cheers,

tony

A
Abhijit Kale 👤 Member for 18 years 11 months

Dear raviraj,



do give me u r email id.



I can give some material on the same.



Regards,

Abhijit

M
Mangesh Khuspe 👤 Member for 19 years 2 months

hi

R$avi can Design Management be included in the manual, coz i have something on it, i am intrested in assisting you in preparing it.



cheers



mangesh


A
A D 👤 Member for 19 years 1 month

Thanks Catalan for the reply,



I do believe, cost and schedule control will be a part of performance measurement baselines control which I proposed in chapter 7 & 8.



RFI’s, NCR’s and submittals can be a part of Integrated Change control system (Chapter 9)



Thanks for the suggestion



Cheers,



Raviraj

R
R. Catalan 👤 Member for 20 years 10 months

Hi Raviraj,



Item 1 to 8 are the detailed part of the Item 9-Integrated Change Control System which is other call it the Cost & Schedule Control.



I would suggest to have a separate chapter on how to develop, implement and track RFI’s, NCR’s, drawings & material submittals, etc., and another chapter for Project Closeout.



Cheers,

A
A D 👤 Member for 19 years 1 month

Thanks Oliver,



For d last four points suggested, i think that shud b a part of SCHEDULE MANAGEMENT SYSTEM, that wud typically focus on what to check in the schedule while submitting; INTERFACES between planning & other departments and the standard reporting formats.



For the remaining points, yes, thats a good suggestion and I will try to incorporate.



Does ur company hav anything as such? If yes, plz mail me.



Cheers,



Ravi

O
Oliver Melling 👤 Member for 19 years 2 months

R,



A manual infers you will are writing a specific how to?



Are you sure it is not a company guide you should be writing that outlines the requirements of the programme and control procedures.



i.e.



Topics covered are:

• Establishing a Work Breakdown Structure

• Production of the Programme

• Approval of the Contract Programme

• Sub Programmes

• Programme monitoring

• Updating the Programme

• Cause and Effect.

• Project Reporting



Details under these headings would include non-project specific guidance such as;



*WBS should be created in conjunction with PM/BidM.

*every activity should have a predecessor & successor.

*performance must be mesured in physical % complete.

*Reports must be presented in company format.

A
A D 👤 Member for 19 years 1 month

Thanks Mike,



Sorry for teh delay, as I was on leave for last 10 days.



Well Mike, I really need some help now. If u have anything, please forward to me, as I have to submit the draft copy by this month end and I have to really dig out some time from this daily BUTTON PUSHING EXERCISE of primavera and excel.



U can mail me at [email protected]



Plz



Cheers,



Ravi

M
Mike Morrison 👤 Member for 18 years 11 months

We have been in the process of trying to develop same thing for about 3 years now, and have made limited progress. I will give you some detailed feedback if you give me a little more time. It was very easy to develop the outline part, but when we do the detailed descriptions it became time consuming and slowed us way down.



The biggest issue is that nobody wants to use it anyway, except the bosses want it because I suggested it.

A
Armando Moriles 👤 Member for 20 years 6 months

Raviraj,



I am interested to know if your manual is a supplementary to your company’s Quality Management Procedure or a standalone document? Also, is it for construction purposes only or does it covers the tender preparation and commissioning stages...



I suggest You may a glossary of terms as appendix to your manual...



Please give me a copy once you have already something to share...





Regards,



Arman

A
A D 👤 Member for 19 years 1 month

Hi Abhi,



Not prepared so far,



Just framed a layout containing the topics. Material not jotted so far.



Do send me with some more topics or paper available



Cheers,

A
Abhijit Kale 👤 Member for 18 years 11 months

Dear Raviraj,



Can you please mail me manual prepared by you.



i ll check it wt ever available with me and revert back to you immediately.



Regards,

Abhijit

A
A D 👤 Member for 19 years 1 month

hey Guys,



41 views, but still no reply



Plz

Forum Sponsor

Top Posters

Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts