Generally during tender there are no detail drawings available, so we have to go for BOQ given by the client.



In case if detail drawings are availabe you can cross check the quantities for the accuracy in your estimated price.

Cheers,

Abhi

J
Johny Kesserwany 👤 Member for 18 years 8 months

By lack of time go by BOQ quantities for the tender! If you get the project you’ll adjust the quantities if needed...



JK

A
Anoon Iimos 👤 Member for 19 years 8 months

you are lucky if you got BOQ and detailed drawings during the Tender Stage,



for me there’s no preffered reference, i suggest you gather as much information that you can

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts