Importing Activity Codes

K
Ken Barrett 👤 Member for 19 years 1 month
A
Andrew Dick 👤 Member for 19 years 4 months

Ken,

Lets first of all presume that your using P5.

That being the case if you create the headers for your codes in a project and then export this to excel, ensuring you select all of the appropriate fields/columns.

You should then be able to populate the excel sheet with a sufficient amount of activities and code them with your codes, and re-import that data.



Also if you are using P5 had you thought about keeping the code at an EPS level instead of a global level - just may save on some clutter for your other users??



Hope this helps

Andy