It is not specifically related to MSP 2003; in fact youll probably have the same issue in MSP 2007 as well. Using any pull-down menu in a cell will cause a restart.
The combination with MS Project and HP fingerprint software (ProtectTools) turns out to be a bad one. Disabling the fingerprint device seems to be an effective workaround for now. To be continued...
you should try to reduce the file size by deleting anu unnecessary item in Tools, Organize; 20 mb is not in proportion with your number of tasks, and much to big for MS Project
Im afraid the problem is not memory related as it occurs with any size file; even one with just two activities.
On my laptop (HP NC4010 with 1Gb RAM) I run up to 25Mb schedules with >10,000 lines and a huge stack of views, filters, modules, groups, etc. etc. and Ive got no issues.
On the PCs that have the problem we have done a complete re-install so all the filters, tables and views are back at the default values. (the problem persists)
I suspect it is related to an MS Office patch (not even necessarily MSP) because these users had no problem until a few weeks ago.
Normally, Im a pretty resourceful guy, but in this case Im clueless to be honest.
I am arunning MSP 2003 Pro and 2007 Std on a AMD Sempron 3000+ based Compaq des ktp, with Windows XP Home SP2, and my MSPs do not crash often.
What is the size of your project files? Both number of tasks and file size, please; your problem could come of a too large number of views, tables, filters, etc... being saved in the file, have a look at Tools, Organize and see how big are the lists in the rightmost column.
We use 2003 Professional, which is indeed relatively stable.
The PCs have been used for quite a while by full-time schedulers who have had no problems with 2003 until a few weeks ago. (The entire department has received exactly the same updates (via Radia) but only three users have the problem.)
Their problems seems to be completely unrelated to the mpp because every schedule crashes.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
We have found the problem!
It is not specifically related to MSP 2003; in fact youll probably have the same issue in MSP 2007 as well. Using any pull-down menu in a cell will cause a restart.
The combination with MS Project and HP fingerprint software (ProtectTools) turns out to be a bad one. Disabling the fingerprint device seems to be an effective workaround for now. To be continued...
H.T.H.
Niek.
Thanks Chaps,
Paul
Paul,
Also remove any unused baselines because these can take up a quite some space.
Also, a "save as" to another file name can help in reducing file size. A 4000-line schedule should be around 6-8Mb.
H.T.H.
Niek.
Paul,
you should try to reduce the file size by deleting anu unnecessary item in Tools, Organize; 20 mb is not in proportion with your number of tasks, and much to big for MS Project
Alexandre
Nieck/Alexandre,
My file sizes are typically 20mb, about 3k -4k lines and a few views filters etc.
The reason I thought memory was some of the MSP messages told me to close other applications blah blah.....
I have increased the virtual memory and it seems somewhat better.
I am going to try having my laptop upgraded to 1gb RAM from 512mb. Ill let you know if it helps
Nieck,
so the only way is to install a fresh MS Windows and MS Office with no patch on your PC
Too bad, that means a good full day of unnecessary work
Alexandre
Im afraid the problem is not memory related as it occurs with any size file; even one with just two activities.
On my laptop (HP NC4010 with 1Gb RAM) I run up to 25Mb schedules with >10,000 lines and a huge stack of views, filters, modules, groups, etc. etc. and Ive got no issues.
On the PCs that have the problem we have done a complete re-install so all the filters, tables and views are back at the default values. (the problem persists)
I suspect it is related to an MS Office patch (not even necessarily MSP) because these users had no problem until a few weeks ago.
Normally, Im a pretty resourceful guy, but in this case Im clueless to be honest.
Cheers,
Niek.
Paul, Nieck,
I am arunning MSP 2003 Pro and 2007 Std on a AMD Sempron 3000+ based Compaq des ktp, with Windows XP Home SP2, and my MSPs do not crash often.
What is the size of your project files? Both number of tasks and file size, please; your problem could come of a too large number of views, tables, filters, etc... being saved in the file, have a look at Tools, Organize and see how big are the lists in the rightmost column.
In case, send the file to my email box: [email protected]
Hope this helps,
Alexandre
I am running 2003 Standard and getting similar problems. However out of 14 people working with it here only I have the problem.
I think it may be memory related?
Will more RAM solve this?
Regards,
Paul
Hi Alexandre,
We use 2003 Professional, which is indeed relatively stable.
The PCs have been used for quite a while by full-time schedulers who have had no problems with 2003 until a few weeks ago. (The entire department has received exactly the same updates (via Radia) but only three users have the problem.)
Their problems seems to be completely unrelated to the mpp because every schedule crashes.
Ive found a similar issue in the MS blog: http://www.microsoft.com/communities/newsgroups/en-us/default.aspx?dg=m…
Cheers,
Niek.
Niek,
MS Project 2003 (Standard, Pro?) is relatively stable, not known for regular crashes.
Does it crash with EVERY project on this PC?
Alexandre