there is a post in P3 forum where one planner suggests that using multiple holidays calendar be assigned to the activity, but during update it will not be accurate. you try..
The feature to split task in MSP does not exist in Primavera. You have to go by adding several activities...
JK
Horlen,
Not sure about P5 as I can not rememeber but in P6 in the activity form you can use suspend option to break an activity but only for once. It might be the same in P5.
For more breaks, Im afraid you will need to add multiple activities.
HIH,
Cheers.
Horlen,
In a nutshell, what you can do is create Steps within the activity in question giving weights to each step proportionate to the effort required of the total budget.
Or if you need to divide the activity into discrete parts so that you can either add logic or divide the costs up, you will need to create New seperate tasks and budget them accordingly, (rebasline those activities if your baseline is at that level too)
My thoughts
Andy