P3e Ver 3.5.1 Original Duraiton changing while upd

A
Afzal Razak 👤 Member for 22 years 3 months
D
David Forrest 👤 Member for 24 years 6 months

Recommend that you check both activity and duration type sand refer to the user manual. Resource dependant tasks can chenge durations if actuals are applied. Durations can change if resources are altered.

D
David Forrest 👤 Member for 24 years 6 months

Recommend that you check both activity and duration type sand refer to the user manual. Resource dependant tasks can chenge durations if actuals are applied. Durations can change if resources are altered.

F
Forum Guest 👤 Member for 17 years 4 months

Hi,

Ok Then just check bars format, and make sure about what kind of summary bar you’ve selected ( current bar summary, first baseline summary, 2nd baseline summary, remaining bar summary..etc.) all the best!

Bye

hadi

A
Afzal Razak 👤 Member for 22 years 3 months

Hi,

Thanks for ur reply. I have Primary Baseline for my current update. BL Start & BL Finish dates are not changing. Only the original duration in the current project summary bar is changing.



Regards

Afzal

H
Hadi k. Shabibi 👤 Member for 22 years 5 months

Hi!

Did you select primary or secondary baseline ?

Did the BL Start & BL Finish changed as well for the activities

Please check that !!I think you need to creat a baseline

and use one of three methods for updating .

Bye

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts