Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Nice trick. Tried this "hammocking" using task with resources assigned/effort driven, seems to work well,could come in handy....good spot.
Plus
a double click on the "linked" start and finish dates
will send the cursor automagically to the "source" dates.
Sure,
task type should be "Fixed Units"; and this pseudo hammock task will work better without any resource assigned.
the small grey triangle is only visible if the option is being checked in Tools, Options, General
Alexandre
This is a great little trick, but in my experience the “Task Type” must not be “Fixed Duration”.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
You will see a small grey triangle in the corner of the cells which are "live" links.
See on the menu EDIT, LINKS.
It is a bit cryptic, not always easy to find which cell the target cell is linked to.
A note in the Notes field of the two Tasks helps a lot.
Thanks! Great!
The more I learn MS Project, the more I get surprised!
But now I have another question, because these Excel-type links can be probably quite confusing:
Suppose I got an MS Project schedule from someone else and I have found linked fields there.
• How do I find out which cell it is actually linked to?
Regards.
This is called a "Hammock" Task.
Copy the Finish Date of Task1.
Select the Start Date cell of Task2.
Edit, Paste Special, Link.
Copy the Start Date of Task3.
Select the Finish Date cell of Task2.
Edit, Paste Special, Link.
Task2 will expand and contract to fill the gap.