by default, each project file uses its own resources; the alternative is to create the resources in a separate file called "Resource pool" or "Resource List" (in MSP 2007), and to use these resources in different projects by Tools, Share resources, Share resources, Using resources from (the resource pool)
it is not possible to mix shared and local resources in MS project, and no other project scheduling software will allow this either; as far as I know, only MS Project Server allows this by making a difference between Entreprise resources stored in the Entreprise Resource List and the local resources stored in the project file; but this is a completely different approach
in the Using resources view, the Project columns applies to tasks, not to resources.
When you share resources between projects, MSP copies all the resources from any project file to any other project file, and you cant say where a specific resource comes from; thats why the appropriate way of doing is to create ALL resources in ONE file only, the resource pool, and only tasks in ALL OTHER files, then to link project files to the resouce pool by sharing resources.
Distinction between local resources created in a project file and global resources created in the ressource pool does not exist
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Assaf,
by default, each project file uses its own resources; the alternative is to create the resources in a separate file called "Resource pool" or "Resource List" (in MSP 2007), and to use these resources in different projects by Tools, Share resources, Share resources, Using resources from (the resource pool)
it is not possible to mix shared and local resources in MS project, and no other project scheduling software will allow this either; as far as I know, only MS Project Server allows this by making a difference between Entreprise resources stored in the Entreprise Resource List and the local resources stored in the project file; but this is a completely different approach
in the Using resources view, the Project columns applies to tasks, not to resources.
Happy New Year,
Alexandre
Hi,
Thats what I meant to do. Each file uses the pool without having its own separate resources.
Sorry if my question was unclear.
Have a great year,
Assaf.
Hi there,
this does not show the project the resource comes from, but the project the resource in being used.
happy new year,
Alexandre
Thanks Trevor! It works!
Assaf,
You can!
In the Resource Sheet View you can show the "Project" field/column and this will show where the Resources come from.
Assaf,
You cannot!
When you share resources between projects, MSP copies all the resources from any project file to any other project file, and you cant say where a specific resource comes from; thats why the appropriate way of doing is to create ALL resources in ONE file only, the resource pool, and only tasks in ALL OTHER files, then to link project files to the resouce pool by sharing resources.
Distinction between local resources created in a project file and global resources created in the ressource pool does not exist
Happy new year,
Alexandre