To create a Graphic View of your resource/cost usage as an S Curve (Cumulative curve) do the following:



1. Add the Resource Usage Profile to your bottom view by going to View, Show on Bottom, Resource usage profile.



2. Right click within the profile and select Edit Resource Usage Profile options.



3. On the Data tab, select whether to display Units or Costs and mark the boxes to show the cumulative curves you want to see.





4. Select the colors for the cumulative curves in the Show Remaining Bars As section.



To print only the cumulative curve section of the layout, perform the following.



1. Go to File, Page Setup, Options tab.



2. Mark only the Profile option in the Print section.





Good luck.



JK




Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts