Planned Value Cost Calculation

J
John Jeffree 👤 Member for 23 years 1 month

You also need to check that the resource planned dates coincide with the activity planned dates. Don’t forget to summarise open projects. For some reason our P3ec has stopped doing it automatically at the end of the day

J
James Shimmon 👤 Member for 19 years 5 months

It might be worth checking in the Project view to see whcih baseline is being used for earned value calculations and also which baseline is being used for summary information.



Shimmo