Hi Annon ,
Thanks for your help. I checked the activities calendar and resources calendar ,they are different. But for the resources calendar I cannot change it , they have been greyed out . I will contact the P5 administrator here. Cheers!!!!
check your calendars, i guess differences between resource calendars and activity calendars affect the calculations