Hi Ismail,



We used slipform in construction of silos in the project that I’m currently working in.

Generally, you can operate the slipform 24/7 but you must have enough steel fixers, general labor, concrete finisher, rc concrete, etc..

You should also consider duration for assembly of the slipform.



Karim

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Hi Ismail,



Pick up the phone and ask Sonia of JBR1 or Tara of JBR3 or



Riswan of DIFC Gate Village or



You can also check with Arabtec their whereabouts



Call BRM.



I agree with Vishwas,



There is a limitation on how high Core Wall will go up.



Cheers,



Charlie

V
Vishwas Bindiganavale 👤 Member for 22 years 2 months

Ismail,



Normally in the UAE (for lift cores), it is 3 mts per day. You wouldn’t get an approval from the consultant for anything more than that.



But, then, slipforms have to be coordinated with crane height - which in turn has to be synchronous with the slabs.



Ultimately, the corewall casting depends on the slab-to-slab cycle.



Happy Planning!

Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts