P3e - Resource

P
Patricia Le Clainche 👤 Member for 19 years 1 month

If I understand your problem correctly :

On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them.



Best regards.