P3e - Resource
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
If I understand your problem correctly :
On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them.
Best regards.