What do you mean by "then select the appropriate table from View, Tables, and maybe fields by editing the Table (View, Tables, More tables)" because you only have these in filter. In group all I have are fileds name, field types and order.
Okay, on the MSP that I am using, it is just one major project with many different clients and tasks for these client. The way the resources are grouped is a selection of 2 PMs, 3-7 BAs, 5-20 Technical staffs for each different task.
What I am looking to produce is a report with all the projects (tasks) with all BAs (the names of this BAs), a monthly view of their assignments, when these assignments finishes, which will be when they are available from and how many hours they are assigned on each Projects (tasks).
This is basically way I am trying to report but I guess I am not knowledgeable enough to use the filter on MSP to produce such view or report. Emmanuel
I wanted to using filters to generate the project or in in Gantt chart (task name), the name of the resources, a monthly view of the assigments, avaliable from and hours avaliable views.
When I try to use the filters (resources filters), there are conflicts (the test value can not be used with the field for the data) resolution.
you cannot use filters with analyse timescaled data; just select the taks BEFORE you launch the process, and click "Selected tasks"
should you prefer to Export the data (File, Save As), select the filter you need in the step Tasks mapping (step #6 if you follow the whole process) in the Export Assistant.
I would use the Group column to display the "role" of each resource; then use the dynamic filter "resource Groups..." to be able to select a specific role from all the roles; and export this filtered list to MS Excel.
I used "role" to mean a the grouping of the resources. one of the roles in Resources will be Project managers another role will be Business Analysts, other role will be IT Supports etc.
I am trying to generate a report of say the BA. I am trying to capture when all the named BAs are allocated to projects and when they are not.
I used "role" to mean a the grouping of the resources. one of the roles in Resources will be Project managers another role will be Business Analysts, other role will be IT Supports etc.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks.
Kool, I will try this again tomorrow. I think the head/brain is gone for today.
Alexandre, Thanks again.
1. customize the gantt chart the way you want
2. group the tasks by using Project, Group
What do you mean by "then select the appropriate table from View, Tables, and maybe fields by editing the Table (View, Tables, More tables)" because you only have these in filter. In group all I have are fileds name, field types and order.
This is right?
OK,
you rather should use Project, Group By, and group the projects tasks by resources groups (BA, ...)
then select the appropriate table from View, Tables, and maybe fields by editing the Table (View, Tables, More tables)
then, insert a page break after each group
and print
Hi Alexandre
Okay, on the MSP that I am using, it is just one major project with many different clients and tasks for these client. The way the resources are grouped is a selection of 2 PMs, 3-7 BAs, 5-20 Technical staffs for each different task.
What I am looking to produce is a report with all the projects (tasks) with all BAs (the names of this BAs), a monthly view of their assignments, when these assignments finishes, which will be when they are available from and how many hours they are assigned on each Projects (tasks).
This is basically way I am trying to report but I guess I am not knowledgeable enough to use the filter on MSP to produce such view or report. Emmanuel
Please explain, I dont understand what you mean, what you want to do
Alexandre
I was not using the analyse timescale in Excel.
I wanted to using filters to generate the project or in in Gantt chart (task name), the name of the resources, a monthly view of the assigments, avaliable from and hours avaliable views.
When I try to use the filters (resources filters), there are conflicts (the test value can not be used with the field for the data) resolution.
Emmanuel
Hi Emmanuel,
you cannot use filters with analyse timescaled data; just select the taks BEFORE you launch the process, and click "Selected tasks"
should you prefer to Export the data (File, Save As), select the filter you need in the step Tasks mapping (step #6 if you follow the whole process) in the Export Assistant.
Alexandre
Hi Alexandre
Didnt work out exporting the data to MSE from MSP. Can you please talk me through using filters, never used them before. Thanks
Emmanuel
Yes, I think the later will probably suit best. I will give it a shot and update.
Thanks a mill.
Emmanuel
You cannot filter the tasks when using analyze timescaled data; you can only select some tasks with the mouse and check the "Selected tasks" option.
You could export all the data from MSP to Excel and the use the database functionnalities in Excel.
Okay, I will try this, I was thinking to use the analyze timescaled data in excel for this but I am not to sure how it will come out.
I am new to MSP being using an in-house prog.
OK,
I would use the Group column to display the "role" of each resource; then use the dynamic filter "resource Groups..." to be able to select a specific role from all the roles; and export this filtered list to MS Excel.
Dynamic filters are the ones with a question mark
Alexandre
Okay,
I used "role" to mean a the grouping of the resources. one of the roles in Resources will be Project managers another role will be Business Analysts, other role will be IT Supports etc.
I am trying to generate a report of say the BA. I am trying to capture when all the named BAs are allocated to projects and when they are not.
Emmanuel
Okay,
I used "role" to mean a the grouping of the resources. one of the roles in Resources will be Project managers another role will be Business Analysts, other role will be IT Supports etc.
I am trying to generate a report of say the BA.
OK, what do you mean by "roles" in MSP Std?
This notion does not exist in MSP Std.
Alexandre
Alexandre
I am using MSP 2003 standard.
Emmanuel
Hello Emmanuel,
Are you using MS Project 2003 Standard or Pro+Server?
Alexandre