Slippage Calculation using Total Float

J
Jeff Limpin 👤 Member for 18 years 8 months
A
Ashok Kamath 👤 Member for 18 years 7 months

Can you not establish your Target Project in the Project Overview dialog box (Targets tab)and have a column in your graphical view that shows Variance Target - Early Finish



Have your Baseline schedule as the first Target Variance column to compare with current.



This should show you a running tally for slippage.

A
Ashraf Jahangeer 👤 Member for 19 years 1 month

Hi There,



The question is how to copy?



Global change is not possible.



Regards,



Ashraf

S
Scott Sando 👤 Member for 18 years 8 months

How about:



Copy the target float figures into a custom field, then create a second custom field subtracting current float from the figure in the first custom field?

L
Larry Rino 👤 Member for 18 years 7 months

Is it really necessary to show the difference (current total float minus the target total float) in P3, if not I suggest to export your P3 data in Ms Excel and put formula in the difference column (present it in Ms Excel).



I hope these helps.

A
Ashraf Jahangeer 👤 Member for 19 years 1 month

I broke my head over it but could not do it through global change.



There is a more crude method of exporting the Target Float and Current Float and importing the difference in a Cutom data column.





Regards,



Ashraf

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts