Can you not establish your Target Project in the Project Overview dialog box (Targets tab)and have a column in your graphical view that shows Variance Target - Early Finish
Have your Baseline schedule as the first Target Variance column to compare with current.
This should show you a running tally for slippage.
Member for
18 years 5 months
Member for18 years6 months
Submitted by Ashraf Jahangeer on Mon, 2007-10-29 00:01
Copy the target float figures into a custom field, then create a second custom field subtracting current float from the figure in the first custom field?
Is it really necessary to show the difference (current total float minus the target total float) in P3, if not I suggest to export your P3 data in Ms Excel and put formula in the difference column (present it in Ms Excel).
I hope these helps.
Member for
18 years 5 months
Member for18 years6 months
Submitted by Ashraf Jahangeer on Tue, 2007-10-23 10:55
Member for
18 yearsRE: Slippage Calculation using Total Float
Can you not establish your Target Project in the Project Overview dialog box (Targets tab)and have a column in your graphical view that shows Variance Target - Early Finish
Have your Baseline schedule as the first Target Variance column to compare with current.
This should show you a running tally for slippage.
Member for
18 years 5 monthsRE: Slippage Calculation using Total Float
Hi There,
The question is how to copy?
Global change is not possible.
Regards,
Ashraf
Member for
18 yearsRE: Slippage Calculation using Total Float
How about:
Copy the target float figures into a custom field, then create a second custom field subtracting current float from the figure in the first custom field?
Member for
18 yearsRE: Slippage Calculation using Total Float
Is it really necessary to show the difference (current total float minus the target total float) in P3, if not I suggest to export your P3 data in Ms Excel and put formula in the difference column (present it in Ms Excel).
I hope these helps.
Member for
18 years 5 monthsRE: Slippage Calculation using Total Float
I broke my head over it but could not do it through global change.
There is a more crude method of exporting the Target Float and Current Float and importing the difference in a Cutom data column.
Regards,
Ashraf