why does budget hrs change when increasing remaining

R
Rodel Marasigan 👤 Member for 19 years 8 months

Donovan,



Mark is correct. Check the settings under Project Screen-> Calculation Tab and un-tick the "Link Budget and At Completion for not started activities". This should answer your query.



HTH,

Rodel