Nar, If you have the weekly quantities related to the consumed manhours, try to derive the weekly manhours from your actual production rates. I expect these manhours came from various quantities of completed work.
If you are trying to generate mapower histogram for the past for which you dont have records, I would ask why do you need that? It wont be any productive exercise.
The best thing is make a plan for the remaining manhours and start recording the actuals in a regular basis. That way after another several weeks, you (or someone in your position) wont be in the same position as you are now.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Karthik
Welcome to Planning Planet.
Some advice - It is not a good idea to respond to a long dead thread - if you need help or advice then start a new topic in the appropiate section.
Regarding your query the best source of cost and resource data is the project BoQ / Cost Plan - speak to the estimator / QS to get to what you want.
If you are working with P6 and your WBS is set up correctly then it should be automatic.
Best regards
Mike Testro
Dear sir,
Good morning everybody, i am new joining in planning planet, i am freshers also,
i expert your guidence and help , i develop myself, pls coud u explain
how to calculate the manhour for overall project, weekly, monthly,
how to calulcate the production rate also
i expert the valuable replay
j.karthik
nscl
Nar, If you have the weekly quantities related to the consumed manhours, try to derive the weekly manhours from your actual production rates. I expect these manhours came from various quantities of completed work.
I.e. Weekly manhours = Weekly production rates /
Weekly quantities
I hope these helps.
If you are trying to generate mapower histogram for the past for which you dont have records, I would ask why do you need that? It wont be any productive exercise.
The best thing is make a plan for the remaining manhours and start recording the actuals in a regular basis. That way after another several weeks, you (or someone in your position) wont be in the same position as you are now.