Import P3 Layout into P6

J
Jeff Limpin 👤 Member for 18 years 9 months
J
Jeff Limpin 👤 Member for 18 years 9 months

Thanks Guys - I believe it always good approach start from the scratch.



Regards,

Jeff

J
James Barnes 👤 Member for 18 years 10 months

Jeff, my reading and understanding of teh situation is the same as Dieter’s



Layouts, filters and that cannot be brought across. Mind you, given how arcane the filter system is in P3, I’m not surprised.



You may be able to do something clever with ODBC to extract the filter data from P3 then copy/paste into the P3e forms but frankly, I’d just write new ones



We are planning a migration from P3->P3e atm and are expecting to write all of our layouts etc from scratch.

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Jeff



The following was taken out of "From P3 to Primavera_V5" on the documentation CD. It is the same for P6.

"Data not converted This section lists the data items that are not converted from P3 to the Project Management module.

■ Layouts, filters, and Global Change, report, and graphic

specifications Layouts, filters, and Global Change and

report/graphic specifications are not converted with the

project; however, sample data is provided for these items in

the Project Management module."



But as it is very easy to create new layouts in P6, for me this never was a problem.

Regards

Dieter

Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts