Presumably progress of the works is behind the original programme and in critical delay, and in the Engineers opinion the delay has been caused by the contractor.
You should submit.
1. A current progress update of the opriginal baseline programme, showing a new forecast completion date.
2. If you, the contractor, considers that all or some of the critical delay to the project completion date is the responsibility of the Employer/Client, then submit the necessary details of the delay.
3. Submit a new baseline programme showing a new forecast completion date. This will show a recovery of the critical delay caused by the contractor or the best-possible new completion date and accepting some of the critical delay to date.