Revised Programme-Clause 14.2

R
Roger Gibson 👤 Member for 25 years 1 month

Khalil,



Presumably progress of the works is behind the original programme and in critical delay, and in the Engineer’s opinion the delay has been caused by the contractor.



You should submit.

1. A current progress update of the opriginal baseline programme, showing a new forecast completion date.

2. If you, the contractor, considers that all or some of the critical delay to the project completion date is the responsibility of the Employer/Client, then submit the necessary details of the delay.

3. Submit a ’new’ baseline programme showing a ’new’ forecast completion date. This will show a recovery of the critical delay caused by the contractor or the best-possible ’new’ completion date and accepting some of the critical delay to date.



Roger Gibson

Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts