Export to MSP

P
Paul Harris 👤 Member for 25 years 2 months

And don’t forget if you load MSP 2007 you will not be able to import or export any MSP files!



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

N
Niek Zonneveld 👤 Member for 21 years 3 months

Oliver,



The answer is no I’m afraid.



If you export to MSP you’ll likely to lose quite a lot more that ’just’ LOE tasks. For instance: secondary constraints, the difference between start and finish milestones, multiple dependencies between activities (SS+FF), your status date, reschedule of the remaining work, multiple resource assignments to the same activity.



Furthermore Primavera is a lot more picky in its start and finish dates. For instance, MSP sometimes starts an activity on Friday 17:00, in P5 this will be Monday 9:00. So it is likely your schedule will be slightly different too. Especially with a schedule in progress!



H.T.H.



Niek.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts