Methodology Manager - Updating Model

K
Karim Mounir 👤 Member for 20 years 2 months

Other idea u can do is to export sch. once used in PM (to be as a template).

When needed just import the xer.

M
Mark Chapman 👤 Member for 20 years 1 month

Ok that was the wrong question really. I shouldnt have had this checked out and its now checked back in. So I can make modifications again.



In the past I have had to check the model out in order to use this as a template in PM. I believe I shouldnt need to do this. So what am I doing wrong?