Export scheduled tasks into MS Project
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Simon,
You just have to create your Excel file the way you want the data to look in MS Project,
then launch MS Project, click File, Open, browse to your Excel file and open it
if the MS Project table is not arranged in the same order as the columns in Excel, you will have to map an import table in File, Save As, ... have a look to the online help for more details
Alexandre