Longest path in the enterprise project schedule issues

P
Paul Harris 👤 Member for 25 years 2 months

Kevin



I have raised this issue with Primavera today. The only way I can find to develop a Critical Path over multiple projects is to:



1. Open the projects and select the default project.

2. Calculate the schedules. It also appears that you have to manually change all the projects Data dates manually.

3. Identify the early finish of all the activities.

4. Set a Project Must Finish by Date in all projects.

5. Recalculate the projects.



Primavera Version 5.0 does not seem to have the option to handle multiple subprojects that P3 has!



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

L
Luca Basile 👤 Member for 22 years 11 months

Hi

Pay attention on how you sort the activities.

It may lead to think that you see a project CP while can have the Enterprise one.





L

K
K D 👤 Member for 18 years 8 months

Hi Kevin.

We think you can try option "Calculate multiple float path" while scheduling.

It can create a longest path throughout your 3 project. You need to group by "Float path" in Activity table.

Thanks

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts