this is way where you don’t have a stop-over to take a nap and have to reach the destination with a basket full of unshattered eggs! safely. I hope you got what i mean!
Member for
22 years 4 months
Member for22 years4 months
Submitted by Mehdi Rashidi … on Sat, 2007-10-27 11:22
I suggest we all just ignore Mr Austins ridiculous posts - they obviously dont attempt to add to the sum of planning knowledge, as David says they are from a recruitment consultant not a planner.
Member for
23 years 7 months
Member for23 years7 months
Submitted by David Bordoli on Thu, 2007-09-20 12:08
Oh how we were all fooled by the once Forensic Claim Analysist, now exposed Recruitment Consultant Chris Austin!
So Chris... do you now understand what the Critical Path is?
As a Recruitment Consultant I doubt you were thinking about the same thing as we planners here - maybe the answer you were looking for was the shortest route to the nearest pub - more your kind of thing eh?
Member for
18 years 3 months
Member for18 years3 months
Submitted by Chris Austin on Wed, 2007-09-05 10:34
critical path is the longest path connecting the critical activiries of a project fom the staring of that project to the comletion date of the project.
by the way, the critical activities are the activities have total float = zero.
the total float is the difference between the early start and late start and the early finish and the late finish.
Member for
18 years 2 months
Member for18 years2 months
Submitted by David Barker on Wed, 2007-09-05 07:04
Member for
21 years 8 monthsRE: What is critical path?
this is way where you don’t have a stop-over to take a nap and have to reach the destination with a basket full of unshattered eggs! safely. I hope you got what i mean!
Member for
22 years 4 monthsRE: What is critical path?
In the critical path method we determine some activities that hanve no total & free slack.
Member for
18 years 7 monthsRE: What is critical path?
I suggest we all just ignore Mr Austins ridiculous posts - they obviously dont attempt to add to the sum of planning knowledge, as David says they are from a recruitment consultant not a planner.
Member for
23 years 7 monthsRE: What is critical path?
Oh how we were all fooled by the once Forensic Claim Analysist, now exposed Recruitment Consultant Chris Austin!
So Chris... do you now understand what the Critical Path is?
As a Recruitment Consultant I doubt you were thinking about the same thing as we planners here - maybe the answer you were looking for was the shortest route to the nearest pub - more your kind of thing eh?
Member for
18 years 3 monthsRE: What is critical path?
Thanks ashraf
Member for
19 years 2 monthsRE: What is critical path?
critical path is the longest path connecting the critical activiries of a project fom the staring of that project to the comletion date of the project.
by the way, the critical activities are the activities have total float = zero.
the total float is the difference between the early start and late start and the early finish and the late finish.
Member for
18 years 2 monthsRE: What is critical path?
give him a break hes only a forensic claims analysis
Member for
18 years 2 monthsRE: What is critical path?
refer to the blogg on terminal float you might get an idea of float from that
Member for
18 years 3 monthsRE: What is critical path?
Sorry to be ignorant, but what do you mean bby float?
Member for
18 years 2 monthsRE: What is critical path?
All activities that have no float defines the critical path