Links between multiple projects
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Tony,
Thanks for that. It pretty much mirrors what Ive ended up doing so at least I now have some confidence that Ive got the best (?) solution.
Bob
Bob,
On one of our programmes, we have the same issue.
What I have done is to ensure that the sub-projects always keeps the same file name (e.g. ProjectXXXX_Master.mpp) and is stored in the same location. At issue, it is given an issue and revision reference (e.g. Issue 01 Rev 01) but only within the header or footer, not in the file name.
When the schedule is updated, first of all the user saves a copy of the file as ProjectXXXX_Iss01_Rev01.mpp, which effectively gives an archive copy. The Master file then has its header updated to show Issue 01 Rev 02 (or whatever convention is used).
In this way, each issue of the schedule can be identified by its unique Issue/Revision reference, whilst the links from the master schedule will always link to the file named ProjectXXXX_Master.mpp.
Hope this is of help.
Hi all,
Further to what Alexandre suggests
I would open and "save as" using always the same
name and location each and every project.
this way links should not be broken
hth
Bob,
unfortunately, MSP builds a file to file link when you want to link two tasks from two separate projects; i.e. you cannot change the name or the folder of either project without losing the link
may I ask why you want to save as projects in this situation?
Alexandre
Alexandre,
Thanks for your response. Each plan has a separate owner and they amend their own plans so I want to restrict each plan to just their relevant content.
Bob
Hi Bob,
Might I suggest convincing your client to purchase Primavera?
There are enterprise packages available which would eliminate the problem of loosing your logic links and enable you to successfully manage multiple projects from a single enterprise.
Failing this, good luck with your quest for a solution within MSP.
Regards
Steve
Bob,
1. have each project owner to schedule his own plan and save it as a separate project in his own folder,
2. open a new empty project file of your own, insert these separate projects into your file; be careful to keep each inserted project summarized to only ONE line to avoid that a newly inserted project become part of the preceeeding one,
3. make sure the projects owners do not move or rename their files; the inserted files must be kept at the same place.
Alexandre