Data transfer was ok - no data lost or modified. Old personal layouts from a freelancer, who left the team, appeared as global layouts.
All performance related to database is significantly better especially:
- Summarize
- Assign a code to many activities (>100) which needed some time is now less than 1 second
- Copy projects - so it should be for maintain baselines as well
- Import.
For bad network - loss of connection from time to time - its as sensible as P5. So, when the error window appears --> more --> ignore and I can work again.
We found some new processes on the database server: purge-delete and others. So the biggest difference we found was in database-related operations - probably for Summarize and Maintain Baselines as well; Ill check.
For your items: did you check the size of the log-file? Maybe it is too big.
It looks good reading from your that performances seems to be better than in P5.
I have to do with P5 still several months I think. But I am impatient to get a feedback of P6 experience, particularly for "Summarize", "Maintain Baselines", two functions that make me turning crazy due to the time it requires, as well as the Tracking View (that I avoid to use till I have such performance trubles).
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello Dieter,
That looks good. I did not way, and I put pressure on my "dear Admin" to get this P6 asap. But I still have to wait for a while I think.
Thanks.
Patricia
Hi all
Some more experience with P6:
Data transfer was ok - no data lost or modified. Old personal layouts from a freelancer, who left the team, appeared as global layouts.
All performance related to database is significantly better especially:
- Summarize
- Assign a code to many activities (>100) which needed some time is now less than 1 second
- Copy projects - so it should be for maintain baselines as well
- Import.
For bad network - loss of connection from time to time - its as sensible as P5. So, when the error window appears --> more --> ignore and I can work again.
Regards to all
Dieter
Hi Dinesh,
I remember that I completely failed to install P5 myPrimavera. I had to ask the support.
Thats why I decided to let the PAR install P6.
Regards
Dieter
Dear all,
How to install myPrimavera? I have followed Primavera documentation to install(Stand Alone), but unfortunately it did not work. Can anybody help.
Thanks in advance.
Dinesh
Salut Patricia
We found some new processes on the database server: purge-delete and others. So the biggest difference we found was in database-related operations - probably for Summarize and Maintain Baselines as well; Ill check.
For your items: did you check the size of the log-file? Maybe it is too big.
Have a nice day/Bonne journée
Dieter
Guten Abend Dieter,
It looks good reading from your that performances seems to be better than in P5.
I have to do with P5 still several months I think. But I am impatient to get a feedback of P6 experience, particularly for "Summarize", "Maintain Baselines", two functions that make me turning crazy due to the time it requires, as well as the Tracking View (that I avoid to use till I have such performance trubles).
Kindest regards.
Patricia