Actual Date / Data Date & Follow-up Methods

A
A D 👤 Member for 19 years

Oops bernard,



AND IMPORTANT THING is u have created program and not PLANNING!!!

A
A D 👤 Member for 19 years

Hi Bernard,



There are different ways of updating like



- On the basis of percent completion

- on the basis of remaining duration (RD)

- By updating the resources



But in any of the case, u need to put up the actual start and actual finish date. Once u insert actual finish date, percent completion will be 100%.



Most widely used method is percent completion.



Or the more easy way of monitoring is adding the resources which will drive the activity. Say concreting of basement raft; Qty is 9000 cum. and u have daily concrete pouring of 900 cum. Then add resource concrete yto the activity and then update how much concrete is poured and what is remaining.



This becomes more easy in case of horizontal spread projects (Like Pipeline, Roadworks etc.)than vertical projects (Like buildings and others)



Cheers,



Ravi

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts