Plan% Column

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Izam,



With P6, you don’t need to perform a global change to show the Plan %, you can simply display the column of Schedule % Complete as long as you have the baseline assign to your current schedule.



Regards,



Arnold