Another solution, is to use Visual Reports. They make Excel or Visio outputs, which are PivotTable/PivotChart or PivotDiagram (You can also make PivotTables with export feature). They all use a kind of map or template, which will be a handy tool, when youre going to repeat they same action.
If you want to view timephased information in MSP then you can use the Analyse Timephased data wizard. First you must select either Gantt Chart, resource usage or task usage view. Then either select a number of tasks or the whole schedule and open the view menu on the top toolbar. From the list select toolbars, analysis and then click analyse time phased data. This launches the wizard and from here you can make a number of selections.
Copy/Paste works quite well, as long as you make sure your columns align.
Another way is to open the Excel file from MS Project and use an import map. (if you open a file in MSP and choose XLS as file format, it will launch the import wizard automatically)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Another solution, is to use Visual Reports. They make Excel or Visio outputs, which are PivotTable/PivotChart or PivotDiagram (You can also make PivotTables with export feature). They all use a kind of map or template, which will be a handy tool, when youre going to repeat they same action.
Hi,
You have two way for this
1- create Dynamik link between Excle and MSP
2- Create Macro with VB or Internal Macro in excel
Yes and no.
Some Project data is available for easy display (Task Name, Task Start, Task Finish, Resource Name, Resource Group).
Some Project data is available only using VBA (Assignment Notes).
Some Project data is simply not available.
What data do you want to move from Project to Excel or from Excel to Project? Will you do this once? Or often?
If you want to view timephased information in MSP then you can use the Analyse Timephased data wizard. First you must select either Gantt Chart, resource usage or task usage view. Then either select a number of tasks or the whole schedule and open the view menu on the top toolbar. From the list select toolbars, analysis and then click analyse time phased data. This launches the wizard and from here you can make a number of selections.
Copy/Paste works quite well, as long as you make sure your columns align.
Another way is to open the Excel file from MS Project and use an import map. (if you open a file in MSP and choose XLS as file format, it will launch the import wizard automatically)
H.T.H.