Heat Tracing Norms.

I
Izam Zakaria 👤 Member for 20 years

Of course ..then I propose to create a new norms...dun too much depends on what their have...planners must creative...

D
DATTATREYA PADHARTHI 👤 Member for 23 years 1 month

Dear Izam,



You got me wrong. I am not talking about the relationship between deliverables.

My query was even after giving ISO’s for the Tracing team, we do not get how many mhrs/time is required for tracing work let alone getting a decent estimate after Layout/design.

This affects completion dates.

Normally when doing an EPCM/LSTK from the start we do have norms, but when the Project reaches a stage where Offshore Works come in piecemeals it becomes difficult to estimate.



Cheers



Dattatreya

I
Izam Zakaria 👤 Member for 20 years

Colleague,



To assign manhours for each deliverables nor CTR (Cost Time Resources based on nos of drawings, philosophy, specification and reports. if u talking bout link, of course Piping isometric will implemented after PDMS model and P&ID firmed out.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts