the only way to open two projects simultaniously is to keep the "crtl"-key pressed and select the projects - either in the projects-view by right mouse-button or by File --> Open. Never I realized, that a project was not closed before others were opened.
Revert the schedule-function is not possible.
As in P3, the first line shows the opened project(s).
but the question is i did not intended to open these two projects simultaneously ( i know how to merge them together)
normally my procedure of switching between projects is, i just go to file menu and without closing the open project, i just scroll down and find the project which is listed there and click on it to open it, and then the second project opens.
1) We had a option in windows menu of p3 to switch between open projects. now using my procedure does those two projects are open at the same time or the first one gets closed and second one remains open.
i am just confused why did the both projects got opened last time in the same layout, coz it was never the same thing before.
if both projects are open at same time how can we revert back to its orignal state ( here primavera fails )(make them separate). coz i think primavera people do not belive in user friendliness.
Sorry, I didnt really undestand your question, but I hope the answer will fit.
It is a standard feature that you can open many projects the same time - limited by your computers main memory and yourself.
If you press "F9", P5 will give a warning that there are different data dates. After youll have pressed OK, it will schedule. If there are no inter-relationships, different data dates dont matter - for my experience. If there are some, Im not sure, but didnt find any up to now.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
hi
dieter thanks for your help.
cheers
mangesh
Hi Mangesh
the only way to open two projects simultaniously is to keep the "crtl"-key pressed and select the projects - either in the projects-view by right mouse-button or by File --> Open. Never I realized, that a project was not closed before others were opened.
Revert the schedule-function is not possible.
As in P3, the first line shows the opened project(s).
Regards
Dieter
hi
dieter really thanks for your reply.
but the question is i did not intended to open these two projects simultaneously ( i know how to merge them together)
normally my procedure of switching between projects is, i just go to file menu and without closing the open project, i just scroll down and find the project which is listed there and click on it to open it, and then the second project opens.
1) We had a option in windows menu of p3 to switch between open projects. now using my procedure does those two projects are open at the same time or the first one gets closed and second one remains open.
i am just confused why did the both projects got opened last time in the same layout, coz it was never the same thing before.
if both projects are open at same time how can we revert back to its orignal state ( here primavera fails )(make them separate). coz i think primavera people do not belive in user friendliness.
anyway thats life.
cheers
Mangesh
Hi Mangesh
Sorry, I didnt really undestand your question, but I hope the answer will fit.
It is a standard feature that you can open many projects the same time - limited by your computers main memory and yourself.
If you press "F9", P5 will give a warning that there are different data dates. After youll have pressed OK, it will schedule. If there are no inter-relationships, different data dates dont matter - for my experience. If there are some, Im not sure, but didnt find any up to now.
Regards
Dieter