Duration calculation in p3 & p5
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
hi
dieter
lots of thanks to you & this PP website, without which life could have been difficult.
my problem was solved with guidance received from u.
keep planning & long live PP
cheers
mangesh
Hi Mangesh
Calenders may seem the same in P3 and P5. But P3 has day or hour, depending on your parameter setting. P5 always has hours per day. This can be different to the parameters under
Admin --> Admin Preferences --> Time Units.
Hours per day maybe is not the same --> Put ot to the same rate, e.g. 8 hours per day.
If you Plan with days in P3, days are stored, whereas P5 always stores hours.
Hope, this will help.
Dieter