Displaying delay of tasks graphically
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
I also agree.
But, what about Technical % complete on a task. Do someone use this data on GANTT chart?
Kindest regards.
Patricia
I agree, baseline and the current bar on the Gantt is the best way.
Ijaz,
I would use either the original baseline bar and the current bar on the GANTT or see if you can create a special bar by using user_start_date fields filtered on critical activities in conjunction with a global change.
You could populate the start date with the baseline start/finish, and the finish date with the actual/planned start/finish.
Andy